高级检索

      南水北调大兴支线顶管下穿铁路路基变形规律研究

      Study on deformation laws of pipe jacking under passing railway in Daxing Branch of South-to-North Water Diversion Project

      • 摘要: 为研究顶管施工下穿对既有铁路路基的影响,依托南水北调配套工程大兴支线顶管下穿京九铁路,通过MIDAS GTS NX数值模拟软件对施工过程进行模拟分析,在施工期间采用自动化监测方法实时监控铁路路基沉降,分析顶管隧道下穿铁路路基所引起的变形规律,对铁路路基沉降槽曲线参数进行了拟合。结果表明:对比数值模拟结果和监控数据的沉降趋势一致,施工期间铁路路基数值模拟的最大累计沉降为5.5 mm,轨道最大累计沉降为1.6 mm。通过对扰动范围内土层进行加固,可以保证铁路线路的正常运营,使穿越影响范围内的结构处于可控状态。

         

        Abstract: To investigate the effects of pipe jacking construction beneath existing railway embankments, this study focused on the pipe jacking tunnel construction of Daxing Branch of South-to-North Water Diversion Project as it passed under the Jingjiu Railway. Numerical simulation of the construction process was conducted using MIDAS GTS NX, while automated monitoring was employed in real time to track railway subgrade settlement. The deformation patterns induced by the pipe jacking tunneling beneath the railway embankment were analyzed, and the settlement trough curve parameters of Railway embankment were fitted. The results showed that both numerical simulation and monitoring data exhibited consistent settlement trends. During construction, the maximum cumulative settlement of the railway embankment reached 5.5 mm based on numerical simulation, while the maximum track settlement was 1.6 mm. Reinforcement of the soil within the disturbance zone ensured safe railway operation, keeping all structural impacts within controllable limits.

         

      /

      返回文章
      返回