高级检索

      2024年湖南“6.16”暴雨滴水岩水库大坝应急抢险研究

      Study on the emergency rescue and response at the Dishuiyan Reservoir Dam induced by Hunan "6.16" rainstorm in 2024

      • 摘要: 受2024年湖南省“6.16”暴雨过程持续作用,滴水岩水库出现水位超正常蓄水位、下游二级坝坡中部突现大面积散浸并伴有8处集中渗漏点和拉裂缝等险情,现场紧急采取了多途径“导渗+排水”措施后,险情依然持续恶化,为成功优化出有效的应急抢险方案,迅速控制并解除大坝险情。本文依据大坝险情现状和实测的大坝岩土体物性参数,利用有限元对应急抢险初步方案实施前后的大坝稳定性进行模拟计算,分析了大坝险情持续发展内因,提出了“下游坡脚增设压脚导渗体+加密加深导渗沟+加密导渗井内排水孔”的优化方案。优化方案实施后,大坝险情成功得到控制并逐渐解除。结果表明:在险情发现时、应急抢险初步方案实施后和优化方案实施后三种状态下大坝稳定性计算值与现场实际情况总体皆较为相符;综合应急抢险初步方案总体上是合理的,大坝险情得到了一定缓解,但依然处于缓慢发展中;优化方案实施后,大坝渗透和抗滑失稳风险完全解除,险情得到有效控制。可见,结合现场实际情况的大坝稳定性有限元计算结果具有较高精度,可指导应急抢险方案的科学改进,为汛期出险堤坝应急处置措施优化提供一定借鉴。

         

        Abstract: Under the sustained influence of the "6.16" rainstorm process in Hunan Province in 2024, the Dishuiyan Reservoir has experienced water levels exceeding its normal storage capacity. In addition, a large area of scattered seepage occurred in the middle of the downstream secondary slope, accompanied by 8 concentrated leakage points and tension cracks,despite the emergency implementation of multiple "seepage diversion + drainage" measures on site, the situation continued to deteriorate. To successfully develop an optimized and effective emergency response plan, it was necessary to rapidly bring the dam emergency under control and resolve it.Based on the current dam risk status and measured geotechnical parameters of the dam body, this study employs the finite element method to simulate and calculate the dam stability before and after the implementation of the preliminary emergency response plan. It analyzes the underlying causes of the ongoing deterioration of the dam risk and proposes an optimized solution involving "adding a seepage-diverting toe weight at the downstream slope toe, increasing the density and depth of seepage diversion trenches, and densifying drainage holes within seepage diversion wells." Following the implementation of the optimized plan, the dam risk was successfully brought under control and gradually eliminated.The results indicate that: The calculated stability values of the dam under three conditions—at the time the risk was identified, after the initial emergency measures were implemented, and after the optimized solution was applied—generally align well with the actual field observations. The preliminary comprehensive emergency rescue plan was generally reasonable, as it provided some relief to the dam's emergency situation, although the situation was still evolving slowly. After the implementation of the optimized solution, the risks of seepage and anti-sliding instability of the dam were completely eliminated, effectively bringing the emergency situation under control. It can be seen that the finite element calculation results of dam stability, which take into account the actual on-site conditions, exhibit high accuracy. These results can guide the scientific improvement of emergency rescue plans and provide valuable reference for optimizing emergency response measures for dams at risk during the flood season.

         

      /

      返回文章
      返回